Outlet pipe for natural gas

Brief description: Completion of the 35-metre-long, 10-tonne natural gas discharge pipe after a four-month construction period.

Industry: Natural gas network

Product group: Plant and pipework

Discharge pipes

The way is now clear at the pumping station

Albrecht Edelstahl was awarded a special contract to manufacture two discharge pipes for the pumping station of a natural gas pipeline. The complete design, testing and logistics – all from a single source.

Production and testing

Albrecht Edelstahl was awarded a special contract to manufacture two discharge pipes for the pumping station of a natural gas pipeline. Albrecht Edelstahl was responsible for the complete manufacture of the pipes, each 35 m long, with diameters of 500 mm and 700 mm respectively, and wall thicknesses of 6 mm and 8 mm respectively. Albrecht Edelstahl was also responsible for non-destructive material testing (including X-ray and pressure testing).

Finally, transporting the two pipes, with a combined weight of 8 tonnes, to their destination proved to be a logistical challenge: loading alone took 1.5 hours. Declared as an oversized special consignment, the journey from Lindlar to the customer’s premises took place under a police escort and with an escort vehicle, travelling overnight from 10 pm.

Over 10 tonnes of stainless steel in a single piece

Completion of a blow-out pipe measuring 35 metres in total length and weighing 10 tonnes

January 2020: The lorry drives out of our workshop and seems to go on forever. On board is a 35-metre-long discharge pipe for natural gas. After four months of construction, entirely in-house, the 10-tonne discharge pipe leaves the apparatus and vessel construction department at W. Albrecht GmbH & Co. KG. It is transported to its destination via a special night-time consignment, complete with an over-length load and an escort vehicle.  

Specifications

  • Natural gas discharge pipe, 35 m freestanding with hydraulic vibration damper
  • Total weight: 10 tonnes
  • Material: 1.4301 
  • Includes signal lighting for air traffic control
  • Designed to withstand pressure surges in the event of ignition, e.g. due to a lightning strike
  • Everything from a single (our) source
    • Project management carried out by our in-house engineers
    • All cutting operations (laser and plasma) carried out in-house
    • All mechanical work and equipment fabrication carried out in-house

Technical details

  • Manufactured in accordance with pressure equipment regulations and EN 1090-3
  • TÜV structural and pressure testing
  • 100% X-ray inspection
  • 100% PMI test
  • 100% penetrant testing

Share article